When CP3 is implemented, please decommission CP5.

Event Timeline

revi created this task.Jul 26 2018, 14:39
revi triaged this task as Normal priority.
Paladox added a subscriber: Paladox.Jul 26 2018, 15:05
revi moved this task from Incoming to Radar on the revi board.Jul 26 2018, 15:16

@revi I will be looking into implementing cp3 as soon as possible (using Snapshots or any other proposal) so that we can decomission cp3.

AmandaCath changed the task status from Open to Stalled.Oct 3 2018, 00:49
AmandaCath added a subscriber: AmandaCath.

No activity since July except for a mention in the recent blog post, therefore this is stalled.

MacFan4000 changed the task status from Stalled to Open.Oct 3 2018, 02:35
MacFan4000 added a subscriber: MacFan4000.

This isn’t stalled on anything

Paladox changed the task status from Open to Stalled.Oct 3 2018, 08:06

It is stalled seeing as if we got rid of cp5 before we can move to cp3 then Asia would have to go through cp2 which means slower loading.

revi added a comment.Sun, Dec 2, 11:50

Seems there's no progress on cp3.

This is my 6 months notice that I will stop paying cp5 after 2019-07-01.

In T3405#73964, @revi wrote:

Seems there's no progress on cp3.

This is my 6 months notice that I will stop paying cp5 after 2019-07-01.

Ok, thank you. That is by far more than understandable, you have already done so much by offering to pay for cp5! Thank you!

Now, with @labster we must decide whether Miraheze would potentially take over payments for cp5, in the case that WMID still does not update us on cp3.

John moved this task from Backlog to Operations on the Goal-2019-Jan-Jun board.Tue, Dec 4, 18:58